When Is an Optimised Asset Actually Performing Near Its Potential?

Optimisation, external performance evidence and the limits of established expectations

When optimisation reaches its apparent limit

An industrial asset may undergo successive rounds of technical and operational optimisation, achieve its approved performance objectives and demonstrate little remaining improvement potential within its established operating framework.

The conclusion may be well supported. Reservoir forecasts may have been updated against production history, facilities constraints examined, operating practices refined and further investment opportunities evaluated. Independent technical assurance may have confirmed the integrity of the analysis.

Yet the conclusion that little further improvement is available depends not only upon the quality of the optimisation, but also upon whether the assumptions, constraints and alternatives defining it adequately represent what might be achievable.

Optimisation is undertaken against specified objectives and within defined constraints. Its results are conditional upon those definitions. The more difficult question arises when the constraints themselves are partly the product of earlier engineering, operating or investment decisions.

A development concept may have been selected from alternatives considered appropriate at the time. A facility’s operating envelope may reflect accumulated experience of equipment reliability and process behaviour. A mature field’s remaining potential may be assessed against a recovery strategy established many years earlier.

Each may be technically defensible within its original context without necessarily remaining the most appropriate basis for assessing future performance.

An organisation can therefore become increasingly confident about the best outcome achievable within its established framework without acquiring equivalent confidence that the framework adequately represents the available possibilities.

The distinction matters when determining whether an apparent performance limit is intrinsic to the asset, reflects an economically justified choice or arises from assumptions that warrant reconsideration.

How performance expectations become embedded

Industrial performance expectations develop through successive decisions rather than a single assessment.

Initial development studies evaluate alternatives and establish technical and economic assumptions. Engineering design converts selected assumptions into physical configurations. Commissioning and operating experience subsequently inform performance forecasts, maintenance strategies and operating limits.

Over time, these decisions create an established framework for assessing performance.

This is necessary. Industrial operations cannot continually reopen every historical decision. Stable operating envelopes, engineering standards and development plans provide the basis for safe execution, accountability and continuous improvement.

The difficulty arises when an assumption originally adopted as a reasonable planning or design choice comes to be treated as an intrinsic limitation of the asset.

A facility operating constraint may have originated in a conservative commissioning assumption. A well configuration may reflect the technology and economics prevailing at the time of development. A production forecast may incorporate a reservoir-management strategy that has subsequently become the accepted reference case.

None necessarily indicates that the original decision was wrong. The question is whether subsequent evidence has altered the basis upon which that decision should now be judged.

This is particularly relevant in long-lived assets, where technology, operating knowledge, infrastructure availability and commercial conditions may change substantially.

Performance against an established expectation is an observation. Whether the expectation itself remains appropriate is a separate interpretation.

Some apparent constraints are unavoidable. Others may be technically alterable but economically justified. Still others may reflect assumptions that have not been sufficiently re-examined.

Distinguishing between these explanations requires evidence beyond the asset’s performance against its existing objectives.

What does independent comparison add to established assurance?

Sophisticated industrial operators already recognise the limitations of internally defined performance expectations.

Major developments undergo concept selection, technical assurance, economic evaluation and independent review. Producing assets are examined through surveillance, performance analysis, redevelopment studies and continuous improvement programmes. External specialists, industry databases and comparative studies may already inform these processes.

Independent benchmarking does not introduce the idea of challenging assumptions into organisations that would otherwise accept them uncritically.

The relevant question is whether existing assessments have access to sufficiently representative external evidence, and whether that evidence has been interpreted in a manner capable of challenging the expectations under review.

Technical assurance may establish that forecasts are consistent with available data, engineering calculations are appropriate and proposed developments satisfy specified requirements. More extensive assurance can also examine alternative concepts, external comparators and underlying assumptions.

Independent comparative assessment is therefore not necessarily separate from, or superior to, established assurance. A comprehensive assurance exercise may already encompass it.

The distinction concerns the enquiry.

One question is whether a proposed decision is adequately supported by the evidence considered. Another is whether the performance expectations against which that decision is evaluated remain consistent with what relevant external industrial experience suggests may be achievable.

The additional contribution of external comparison arises where it introduces observations, alternative explanations or development possibilities not adequately represented in the existing assessment.

Its value is conditional. It may corroborate established conclusions, identify an unexplained difference or reveal that the original question has been framed too narrowly.

Its authority derives from the quality of the evidence and reasoning, not simply from the independence of the assessor.

From observed difference to technical enquiry

External benchmarking can identify performance differences, but those differences acquire significance only through technically defensible interpretation.

A higher recovery factor, greater LNG throughput, lower capital intensity or shorter project schedule is not, by itself, evidence of superior operating or development practice.

The relevance of a comparison depends upon the question being examined and the extent to which material differences in circumstances can be recognised.

A comparison appropriate for reservoir recovery mechanisms may not be suitable for evaluating development economics. LNG facilities with similar nominal capacities may differ materially in feed-gas characteristics, process configuration or operating requirements. Projects with similar production capacities may involve different infrastructure and technical complexity.

Observed performance differences may reflect measurable technical conditions, development choices or circumstances not adequately represented in the available evidence.

An unexplained difference is not automatically an improvement opportunity. It may instead raise questions about the relevance of the comparison, the adequacy of the prevailing interpretation or the existence of constraints that have not been sufficiently recognised.

This is where comparative judgement becomes more consequential than ranking.

A quartile position describes where an asset sits within a selected distribution. It does not establish why the asset occupies that position or whether its performance is close to what is realistically achievable.

The distinction between internal improvement and external performance assessment has long been recognised at the highest levels of the industry.

In December 2004, Shell’s Group Chief Executive, Jeroen van der Veer, stated:

“Doing it better than yesterday is fine, but doing it better today than the competition motivates me more.”

He associated first-quartile performance with an external mindset and described the Executive Committee’s interest in monitoring the proportion of Shell assets achieving first-quartile performance.

The principle remains relevant. However, external ranking and assessment of achievable potential are different enquiries.

A first-quartile position establishes relative standing within a defined comparator population; it does not independently explain performance differences or establish what a particular asset could reasonably achieve. Equally, an asset below the first quartile is not necessarily underperforming relative to its own potential.

The more demanding question is whether relevant external evidence supports, challenges or leaves unresolved the assumptions underlying existing performance expectations.

LNG assets – distinguishing operating constraints from achievable limits

LNG facilities illustrate how apparent performance limits arise from interacting process, mechanical, operational and commercial conditions.

A facility may achieve high availability, meet its production plan and demonstrate effective maintenance performance while operating within an established throughput envelope.

That envelope may reflect process design, feed-gas composition, ambient conditions, rotating-equipment capability, equipment reliability, safety requirements and contractual obligations.

Some constraints are intrinsic to the facility’s configuration. Others depend upon operating choices or assumptions that may change over time.

Consider an illustrative facility that has undergone extensive operating optimisation and debottlenecking studies. Management concludes that further sustained production increases require substantial capital expenditure.

Relevant external experience may include facilities with similar nominal capacities that have achieved higher sustained throughput.

The observation does not establish an improvement opportunity.

Differences in feed-gas composition, inlet conditions, ambient temperature, process configuration and operating requirements may explain much of the apparent performance variation.

Even where material differences remain insufficiently explained, they do not necessarily indicate avoidable operating constraints. Maintenance strategies, rotating-equipment limitations and process operating requirements may reflect legitimate technical, reliability or commercial considerations.

Nor would evidence of more favourable performance elsewhere establish that adopting another facility’s practices would reproduce its outcome. Technical applicability, reliability consequences, operating risks and economic attractiveness remain material considerations.

External evidence may nevertheless raise legitimate questions about whether particular operating assumptions continue to provide the most appropriate basis for an investment decision.

For example, an assessment concluding that additional production requires substantial capacity investment may warrant reconsideration if relevant industrial experience suggests that some established constraints are potentially alterable.

Equally, the evidence may confirm that facility-specific limitations make the proposed capital investment necessary.

The purpose is not to presume that additional production is available, but to establish whether the operating assumptions informing a consequential decision remain defensible.

Maturing basins – when the explanation extends beyond the reservoir

Maturing hydrocarbon basins present a different challenge because recovery performance and remaining economic potential depend upon the interaction of subsurface behaviour, wells, production facilities, infrastructure and development choices.

Operators typically possess extensive knowledge of reservoir behaviour, production history and remaining resources. Nevertheless, an observed recovery difference between apparently comparable fields may not be adequately explained within a reservoir-only interpretation.

Consider an illustrative mature field whose recovery factor appears unfavourable against relevant reservoir analogues.

Geology, reservoir heterogeneity, displacement mechanisms, well spacing and injection performance may account for important differences between fields.

However, recovery outcomes can also be materially influenced by development and operating circumstances extending beyond the reservoir.

Produced-water handling capacity, artificial-lift limitations, well intervention economics, infrastructure availability and the expected remaining life of shared facilities may influence development strategy and ultimate recovery.

A field with technically attractive remaining resources may have experienced restricted development because of infrastructure or economic constraints rather than reservoir limitations alone.

Conversely, apparently superior recovery elsewhere may reflect different investment conditions or infrastructure availability.

These distinctions matter because reservoir recovery potential, technically achievable development outcomes and economically preferred development strategies are not necessarily equivalent.

The UK Oil and Gas Authority’s Recovery Factor Benchmarking report, published in September 2017, estimated that increasing recovery factors across a prioritised selection of large UK Continental Shelf oilfields could yield an additional 900 million barrels of oil.

The estimate illustrated the potential significance of recovery-factor differences, but did not establish that the additional volumes would necessarily be technically or economically recoverable in every case.

Additional production may require wells, facilities investment, extended infrastructure operation or substantially greater expenditure. The technically achievable recovery outcome is not necessarily the economically preferred development outcome.

Where external recovery experience raises questions that cannot be adequately resolved through subsurface considerations alone, the consequential issue may concern the development strategy, infrastructure assumptions or economics governing remaining production.

The question can change from how to improve reservoir recovery to whether the current development pathway remains the most defensible means of converting remaining resources into economic value.

A broader perspective is relevant where the industrial evidence warrants it, not because every recovery comparison requires examination of the entire value chain.

Field development plans – when the selected concept deserves reconsideration

Field development planning illustrates the distinction between optimising a selected concept and establishing whether that concept remains appropriate.

Development concepts are selected through technical and economic evaluation of alternatives. The preferred concept is then refined through reservoir studies, well planning, facilities engineering, cost estimation and risk assessment.

The resulting plan may be extensively optimised and independently assured.

However, that does not necessarily establish the continuing appropriateness of the concept itself.

This is not an argument for repeatedly reopening concept selection. Development decisions require commitment, and alternatives legitimately rejected under established conditions should not be reconsidered without reason.

The issue arises when material changes in reservoir understanding, technology, infrastructure availability, costs or commercial conditions alter the basis of the original selection.

A concept selected when particular drilling technologies, infrastructure options or capital costs made alternatives unattractive may remain internally coherent even after those circumstances have changed.

Relevant external experience may include developments employing different well configurations, recovery strategies, production-system designs or development sequences.

Differences in reservoir conditions, objectives or commercial circumstances may explain their apparent advantages. Nevertheless, credible external alternatives can raise legitimate questions about assumptions underlying an established development concept.

Where those questions have material technical or commercial consequences, strategic reassessment may be more appropriate than further optimisation of the selected concept.

Whether to reopen concept selection depends upon the significance of the evidence, the consequences of retaining the existing concept and the cost and risk of reassessment.

The governing question is whether the evidence supporting the concept’s continued selection remains sufficiently robust.

Capital projects – when the baseline is the question

Major oil and gas capital projects are developed and executed through engineering, cost estimation, scheduling, quantitative risk analysis and project assurance.

Once a baseline is approved, performance management concentrates on delivery against defined cost, schedule and scope expectations.

These controls are essential. They do not independently establish whether the expectations incorporated into the baseline were appropriate.

A project may be delivered within budget and schedule while its capital intensity or development duration remains materially different from relevant external experience.

Conversely, a project exceeding its original baseline may have encountered circumstances that make its eventual performance defensible against comparable developments.

Neither conclusion follows from baseline variance alone.

The approved baseline reflects earlier choices concerning project scope, development configuration, technical complexity, contracting arrangements, market conditions and execution strategy.

Some may influence eventual performance more substantially than the effectiveness of execution against the baseline.

Flyvbjerg’s work on reference-class forecasting examines how historical project outcomes can inform assessments of cost and schedule risk, including limitations of estimates developed principally from an internal project perspective.

Reference-class forecasting and independent assessment of achievable project performance are related but distinct.

Historical outcome distributions can inform the realism of cost and schedule expectations. Establishing whether a particular project could reasonably have achieved a different outcome also requires consideration of scope, technical complexity, execution conditions and development choices.

This distinction is particularly relevant before final investment decision.

An extensively assured project may have cost and schedule expectations that remain materially different from relevant external experience because of its concept, contracting approach or scope assumptions.

Comparison may confirm that those differences are justified or identify assumptions requiring further examination before substantial capital commitments become difficult to reverse.

The question is not only whether the project can be delivered against its approved baseline, but whether the baseline reflects defensible expectations given the project’s characteristics and available alternatives.

What AI changes – and what it does not

Artificial intelligence is extending the analytical capabilities available to industrial organisations.

AI-assisted methods can process extensive datasets, support forecasting, evaluate operating configurations and investigate alternatives that would otherwise be difficult or time-consuming to examine.

These capabilities may improve optimisation and the assessment of established assumptions, although better analytical performance does not automatically translate into superior engineering or commercial outcomes.

There is no inherent reason why AI must reinforce an existing operating or development framework. Its contribution depends upon the questions examined, the alternatives represented and the evidence available.

A highly accurate production forecast under an established reservoir-management strategy does not establish that the strategy is preferable to credible alternatives.

Similarly, an optimisation algorithm may identify an effective operating configuration within specified constraints without establishing whether those constraints are intrinsic or economically justified.

AI can reduce uncertainty about outcomes within a defined analytical framework while leaving unresolved uncertainty about the appropriateness of that framework.

This limitation also applies to conventional engineering models, optimisation methods and project forecasts.

AI systems informed by appropriate external evidence may help challenge established assumptions and identify performance differences that warrant further consideration. Their practical significance remains a matter of evidence and technical judgement.

A model may perform reliably within its intended scope while the industrial decision requires evidence extending beyond that scope.

Independent comparative benchmarking is therefore not a substitute for model validation or AI governance. Its relevance lies in assessing whether the performance expectations informing consequential decisions remain defensible against relevant external experience.

When is the evidence sufficient?

External benchmarking cannot establish achievable potential simply by identifying superior observed outcomes.

Comparative evidence may be incomplete, relevant external experience limited and differences in operating or development circumstances difficult to explain.

In some cases, the evidence supports the existing interpretation of performance. In others, it identifies a difference warranting investigation without establishing whether a different outcome is achievable.

Occasionally, it identifies a credible alternative with sufficiently strong technical and economic support to justify reconsidering an operating or investment decision.

These conclusions should not be conflated.

The standard of evidence depends upon the decision.

A relatively inexpensive operating trial may be justified by a plausible but uncertain opportunity. A major redevelopment, capacity expansion or irreversible capital commitment requires stronger evidence concerning technical feasibility, economic consequences and risk.

The relevant question is whether the evidence is sufficient to support the decision being considered, including the decision to investigate further, retain the existing strategy or commit additional capital.

Independent judgement matters because comparative evidence does not interpret itself.

A defensible independent opinion must recognise the relevance and limitations of the comparative evidence, the credibility of competing explanations and the uncertainty surrounding established performance expectations.

Independence also requires the freedom to conclude that no material improvement opportunity has been demonstrated.

A benchmarking exercise designed to identify underperformance regardless of the evidence is no more defensible than an internal assessment designed to confirm existing expectations.

The objective is to establish what the evidence permits management to infer and where material uncertainty remains.

The question beyond optimisation

Industrial optimisation and technical assurance improve performance, inform investment decisions and reduce uncertainty within defined engineering and commercial frameworks.

Their sophistication does not, by itself, establish the adequacy of the assumptions defining those frameworks.

External comparative evidence provides an independent perspective on whether established expectations remain consistent with relevant industrial experience.

Its value lies not simply in identifying higher-performing assets, but in informing judgements about the assumptions, constraints and alternatives underlying consequential operating and investment decisions.

Sometimes the evidence confirms existing expectations. Sometimes it supports reconsideration of an established decision. Sometimes it reveals uncertainty requiring further investigation.

The distinction is particularly consequential where investment commitments are substantial, development choices difficult to reverse or operating strategies have remained in place over long periods.

Greater analytical sophistication, including AI, does not remove the need to establish whether the expectations governing a decision remain technically and economically defensible.

When rigorous optimisation concludes that little further improvement is available, what evidence would establish that the apparent limit belongs to the asset rather than to the framework within which it has been assessed?


References and further reading

  1. Van der Veer, J. (2004). Van der Veer speech – full text. Speech delivered in The Hague, 15 December 2004. Financial Times, 15 December 2004. https://www.ft.com/content/73797c54-4ed2-11d9-9488-00000e2511c8

  2. North Sea Transition Authority. Asset Stewardship Expectations. https://www.nstauthority.co.uk/regulatory-information/exploration-and-production/stewardship/expectations/

  3. Oil and Gas Authority (2017). Recovery Factor Benchmarking. Published 7 September 2017. https://www.nstauthority.co.uk/news-publications/recovery-factor-benchmarking-report-published/

  4. Flyvbjerg, B. (2006). From Nobel Prize to Project Management: Getting Risks Right. Project Management Journal, 37(3), 5–15. https://doi.org/10.1177/875697280603700302